JACKSON – Jackson Township MUA has come up with a tentative schedule for paving for the water main trench work to be done on Anderson Rd., Patterson Rd. and West Commodore Blvd.
The schedule follows:
- Week of April 1: Six Flags Great Adventure & Route 537, expected to last 3 days
- Week of April 8: Anderson Rd., expected to last 5 days
- Week of April 15: Cassville Rd. crossing & Patterson Rd., expected to last 2 days
- Week of April 15 (and possibly into week of April 22): W. Commodore Blvd, expected to last 5 days but could extend into the following week
Jackson MUA’s contractor will be following the same traffic control plan that was used to install the water main, which allows for milling one day and then paving the next day.