SUEZ To Begin Night-Time Roadway Paving Downtown

Photo by Jason Allentoff

  TOMS RIVER – After upgrading aged water mains, SUEZ crews will begin a series of night-time roadway paving projects throughout the downtown area. These upgrades will help ensure water service reliability and quality for residents in Toms River.

  The paving is slated to start on April 15 through April 22 in the Hooper Avenue and Washington Street neighborhoods, weather permitting.

  “While there will be slight inconveniences due to road closures and detours, our crews will be working quickly and carefully, which will result in safer roadways and paved surfaces following water main construction,” Director of Operations Jim Mastrokalos said. “Access will be maintained to all residential and commercial buildings during the work, and emergency vehicles will have access to local properties throughout the project.”

  Paving will be completed at night during the week with crews working from around 7 p.m. to 6 a.m. with police and traffic control on site. Residents are asked to plan for delays due to the project. There is no weekend paving.

  “The crews begin with a milling operation, which consists of removing approximately two inches of old pavement followed by replacement of new asphalt,” Mastrokalos said. “There will be some temporary interruptions to the regular flow of traffic where the paving project will take place, and motorists are urged to use caution while traveling through the construction zones.”

  The intended schedule of streets to be planed and resurfaced during this phase of the project are as follows:

April 15:  Washington Street, beginning at Lexington Avenue to Main Street (westbound)

April 15:  Hyers Street from Legion Court to Washington Street

April 18:  Brooks Road, Dock Street, Maiden Lane

April 18:  Washington Street, beginning at Lexington Avenue to Main Street (eastbound)

April 19:  Hooper Avenue, beginning at Grand Avenue to E Water Street

April 20:  Robbins Street from Washington Street to E Water Street

April 20:  Allen Street from Washington Street to E Water Street

April 21:  Washington Street asphalt patch (eastbound)

April 22:  Washington Street asphalt patch (westbound)

  In addition, final paving schedules for other recent water main replacement areas including Batchelor Street, Dickenson Avenue, Lafayette Avenue, Lowell Avenue, Marian Street, Russo Place and East and West Woodland Avenues will be announced in the weeks ahead.

  Customers with questions can call 877-565-1456 or visit the SUEZ website at mysuezwater.com.